Panel upgrade permit and inspection
A panel upgrade needs a city electrical permit and a passed inspection before the utility reconnects power. In the sequence cities publish, the utility service order comes first, then the permit, then the swap, then inspection and meter release.

The short version
Cities treat a new or replaced panel as permit work. The city inspects it, and the utility will not reconnect a service until the city says the work passed. The steps below follow the pattern cities such as Laguna Niguel publish. Yours might shift a step or two, and your city’s handout beats any general page. The electrical permits guide covers permits across the region.
Step 1: utility first
Most of the delay lives here, so start here. The electrician contacts the utility service planner for the address: SCE or SDG&E in most of the region, LADWP in much of Los Angeles, or a city utility such as Pasadena, Burbank, Glendale, Anaheim or Riverside. The planner gives the requirements, approves a changed meter location and sets up the disconnect. Laguna Niguel states that a copy of the SDG&E or SCE service order is required before it issues the permit. The utility coordination guide lays out the differences.
Step 2: the permit
The city building department takes the application. Expect these items:
- the address and the work description (for example “replace 100 amp panel with 200 amp, outdoor rated”),
- the contractor’s license information, or an owner-builder statement,
- a load calculation or single-line diagram if the city asks for one,
- the utility service order.
Fees are set by each city and are published on its fee schedule. No single figure applies across SoCal.
Step 3: book the disconnect and the inspection
The utility cuts power for the swap. Laguna Niguel says the utility generally disconnects in the morning and reconnects in the afternoon when the panel passes the preliminary inspection, and tells you to call in the inspection request the day before the utility date. SDG&E guidance for meter panel jobs describes the same pattern, with the city telling SDG&E when the work passes. If the panel moves, the disconnect and the inspection are scheduled separately.
Step 4: the swap
Power is off for most of a working day. The electrician installs the new panel and connects each circuit. Items that the 2022 and 2025 codes add:
- a surge protective device (230.67), Type 1 or Type 2, inside or next to the panel, on new and replaced dwelling services,
- an emergency disconnect (230.85) outdoors for one- and two-family homes, marked as such.
California’s 2025 Electrical Code took effect January 1, 2026 and is based on the 2023 NEC.
Step 5: the inspection
The inspector checks the work against the code and the city list. Laguna Niguel’s list includes:
- an electrical permit and inspection card posted on site,
- the panel secured to a framing member, the dead front in place, and every circuit labeled,
- one wire per breaker, neutrals and grounds landed correctly,
- 240-volt breaker handles tied together with listed handle ties,
- a grounding conductor sized from the data plate, bonded to the water and gas pipes, with an accessible ground electrode,
- 36 inches of clear space in front and 30 inches across,
- empty knockouts plugged and unused wires capped.
Step 6: release and reconnect
When the panel passes, the city releases the meter to the utility, and the utility reconnects. For LADWP jobs inside the City of Los Angeles, the Department of Building and Safety sends its release to LADWP after the final inspection, and LADWP can then schedule its meter work. Open your LADWP service account early, because LADWP says final work waits on it.
If something fails
The electrician fixes the item and the inspector comes back. Check what the city wants for a reinspection fee and notice. To lower the odds, use the prep guide for the electrician visit, keep the panel area clear, and be home for the inspection.
After it passes
Keep the signed permit card. It proves the work was inspected, which matters when you sell. The timeline guide covers how long the whole job runs from first call to restored power.
How the job goes
- Contact the utilitythe service planner at SCE or SDG&E, or LADWP, sets requirements and a disconnect date, and issues the service order.
- Pull the permitthe electrician applies at the city building department and shows the utility service order if the city asks for it.
- Schedule the disconnect and inspectionthe utility cuts power in the morning and the city inspector is booked, often the day before the utility date is confirmed.
- Swap the panelthe electrician installs the new panel, grounding, bonding and surge protective device.
- Pass the city inspectionthe inspector checks the work against the code and the city checklist.
- Release and reconnectthe city releases the meter to the utility, which restores power, often the same afternoon.
Questions people ask
Who pulls the permit for a panel upgrade?
The licensed electrician usually pulls it, and the permit lists that contractor. An owner-builder can pull permits in some cities, but the owner then signs an owner-builder statement and takes on the responsibility. Utilities may still require a licensed contractor for their disconnect and reconnect, so ask your city and utility.
How long does the inspection take?
The inspection visit itself is short, often under an hour. Scheduling is the variable. Laguna Niguel advises requesting the inspection the day before the utility date. Many cities book next-day inspections, but not all do, so ask the building department for its booking window before you set the disconnect date.
What happens if the inspector fails the panel?
The electrician fixes the listed items and books a reinspection. Power stays off or the city may hold the release, depending on the item. Common correction items are unlabeled circuits, double-tapped breakers, missing bonds and missing clearances. A good prep list prevents most of them.
Will the permit show in the sale of my home?
Yes, it is a public record at the city. A final signed permit card shows the work was inspected, and buyers' agents and inspectors often ask for it. Keep a copy of the signed card and the plans with your home records.
Does the utility charge for the reconnection?
That depends on the utility and the job. Some utilities charge for work on their side, such as a new service lateral. LADWP says charges must be paid before it installs meters. Ask the utility planner for its fees up front, and keep them separate from the electrician's quote.
Keep reading
Electrical panel upgrades in Southern California: when and how
A panel upgrade replaces the main breaker box, and most SoCal homes that need one are moving from 60 to…
Electrical permits in Southern California: what needs one and who pulls it
What needs an electrical permit, who pulls it, what the inspector checks, and what happens if the work was…
Who files, who pays and who to call in a service upgrade
The four parties in a panel or service upgrade, what each files, what each pays and what to say when you call.
Panel upgrade timeline: permit, meter spot, disconnect, inspection, reconnect
The step-by-step sequence of a panel upgrade, and where SCE, SDG&E, LADWP and city utilities each add…
Meter, meter socket and service mast
The mast and meter socket are yours, and the meter and the wires to it belong to the utility. Moving or…
How to prepare for the electrician's visit
A ten-minute checklist: panel photos, clear work space, utility data, appliance list, HOA papers and the…
200 amp panel upgrade: what changes and when you need it
A 200 amp panel upgrade swaps your old main panel for a new one and, usually, the wire from the meter to…
Send a photo, get a range.
Share your ZIP and a photo of your panel. Your request goes to a licensed partner electrician, who contacts you.
Get this quoteAurion Electric is a referral service operated by Roviq LLC. Electrical work is done by a licensed partner electrician.