Meter, meter socket and service mast

The mast and meter socket are yours, and the meter and the wires to it belong to the utility. Moving or replacing either one usually moves a panel upgrade from the $2,500 to $4,500 range into the $5,500 to $10,000 range.

  • Your side: Mast, meter socket, panel
  • Utility side: Meter and service lines
  • Harder-job range: $5,500 to $10,000

Get a quote

A service mast and weatherhead rising from a meter past a tile roof edge

Which parts are which

Looking at the outside of a house from the street, you can see four parts in a line.

  1. The service drop or underground lateral. The utility’s wires coming to the house.
  2. The service mast. On an overhead service, the pipe that rises from the meter socket or the roof so the wires clear the roof and ground. It is rigid conduit.
  3. The meter socket. The box on the wall where the utility’s meter plugs in.
  4. The main panel. Often right behind the meter, or inside.

The utility owns the meter and its lines. You own the mast, socket, wiring and panel. This matters because each side has its own rules, and the utility can say no to a change on its side.

When the mast or socket must change

A panel upgrade does not always touch them. The electrician replaces them when:

  • the socket is rated below the new service, for example a 100 amp socket for a 200 amp service,
  • the socket is cracked, corroded or has burned contacts,
  • the mast is too small for the new conductors, or pulls away from the wall,
  • the mast no longer clears the roof or the required height,
  • the utility or inspector flags clearances to windows, gas meters or other equipment.

On a 200 amp service, one city chart lists 2/0 AWG conductors in a 1-1/2 inch rigid mast or riser. For 400 amps the same chart lists 2-1/2 inch conduit. These come from one city’s list, so your table may differ.

Rules inspectors check

Laguna Niguel’s checklist is a typical sample. It asks for:

  • meter height between 4 ft 6 in and 6 ft 3 in above finished grade,
  • a clear working space of 36 inches in front and 30 inches wide,
  • an outdoor-listed panel if it mounts outside,
  • approval from the utility for any change in location, with the working clearances kept,
  • stucco repair that includes proper flashing and wire lath lapped as listed.

Underground conduit replacement is inspected by the utility. And the city requires underground service for new service or reconstruction of more than half a building. That is a local rule.

Emergency disconnect

Since January 1, 2023, California’s code (230.85) has required one- and two-family homes to have an emergency disconnect in a readily accessible spot outdoors. It must be marked “EMERGENCY DISCONNECT”. Some homes meet this with a main breaker panel outside. Others add a listed disconnect next to the meter. If you are changing the meter area anyway, this is the time to settle it.

Utility differences

SCE. The electrician contacts the SCE service planner first, before the panel goes in. The city has to clear the job before SCE sets the meter. Cities that publish the sequence, such as Laguna Niguel, ask for the SCE service order before they issue the permit.

SDG&E. Guidance from SDG&E for meter panel work says the electrician schedules the disconnect with SDG&E and the city inspection, and the city tells SDG&E when the work passes. If the meter panel moves, inspection and disconnect are scheduled separately, and the city informs SDG&E within two business days.

LADWP. LADWP handles load changes and meter work under its Electric Service Requirements. Inside the City of Los Angeles, the Department of Building and Safety inspects the work, and once it passes, the approval goes to LADWP, which then schedules the meter. LADWP has said charges must be paid and a service account opened before it sets meters, so do both early or power can be delayed.

Other utilities, such as Pasadena, Burbank, Glendale, Anaheim and Riverside, each run their own rules. The utility coordination guide lists differences.

Cost

A swap with the meter and mast in place is in the $2,500 to $4,500 range. A new service run, a meter or mast relocation, trenching or stucco work puts the job at about $5,500 to $10,000 as of October 2026, per the panel upgrade cost page. Add the utility’s own charges, which the electrician cannot predict. The timeline guide covers how long meter work can run.

Fire areas

Homes in high fire hazard areas can also face extra local rules and power shutoffs. See wildfire zones and electrical work.

Diagram of the path from the utility pole through the meter and main breaker to household circuits
Where the utility side ends and your side begins. Illustration, not a photo of a specific job.

Questions people ask

Who owns the electric meter and who owns the meter socket?

The utility owns the meter. The homeowner owns the meter socket (the box it plugs into), the mast or conduit, and the wires from the socket to the panel. The utility owns the lines up to the house, with a utility-specific point where its side ends. That split decides who is allowed to touch each part.

Can the electrician move my meter?

An electrician can build the new socket, mast and wiring, but the utility must approve the new location first and does its own disconnect and reconnect. Cities also require clearances and a permit. Expect more than the cost of a straight swap, since the work includes new conduit and often wall repair.

How high should the meter be?

It depends on the utility and the city. One city checklist (Laguna Niguel, updated January 2026) says 4 ft 6 in minimum to 6 ft 3 in maximum above finished grade. Your utility's service requirements document and your city checklist set the number for your address, so confirm both before ordering equipment.

Do I need an underground service?

Sometimes. Laguna Niguel requires underground service for new service or reconstruction of more than 50 percent of a home, and its utility inspects replacement of underground service conduit. Other cities differ. If you rebuild after a fire or do a major remodel, ask the city early, since trenching changes cost and schedule.

Keep reading

Send a photo, get a range.

Share your ZIP and a photo of your panel. Your request goes to a licensed partner electrician, who contacts you.

Get this quote

Aurion Electric is a referral service operated by Roviq LLC. Electrical work is done by a licensed partner electrician.

Call (909) 552-7102Quote