Smart panels, load managers, circuit sharing and lower-power equipment can keep a house on its current service. How the code treats each one, and when a full upgrade is still the answer.

  • Checked: November 2026

Send photos of my panel

A heat pump outdoor unit on a pad with a copper line set and a disconnect box
Control setting80%of the service rating. A 200 A service gets a setting of 160 A or less LBNL
Circuit sharingLarger load onlytwo loads that cannot run together count once, at the larger LBNL
Smart breakersUp to 6 spacestwo for the device, two for the control, two for metering, in some systems LBNL
RMLD load managementUp to $1,200of equipment cost, for smart panels and similar RMLD

The short version. If the load worksheet says "tight" or "over", you have choices besides a bigger service: choose lower-power equipment, share a circuit between two loads that will not run together, or add a device that limits total current. These work on paper only if your inspector accepts them, so ask early. And a full upgrade is still right when there is no room in the panel or the panel itself is the problem.

The idea in one picture

A service has a ceiling. A control device keeps the controlled loads from crossing a line set at 80% of it. The code lets the electrician use that line, instead of the sum of nameplates, as the load.

A control setting at 80 percent of a 200 amp serviceA 200 amp service bar with a line at 160 amps, 80 percent. Loads below the line run freely. A load manager pauses a controlled load such as an EV charger when the total would pass the line. Below, a clothes dryer and an EV charger share one circuit through a switch that lets only one run at a time.200 A serviceControl setting: 160 A (80%)Loads run freelyHeld backClothes dryerone 240 V circuitEV chargerpauses for the dryerOne at a timeCircuit sharing, the simplest controlOnly the larger of the two loads counts
Arithmetic: 80% of 200 amps is 160 amps. The 80% setting and the dryer and EV charger example are from LBNL's service guide. Source.

The options side by side

OptionWhat it doesHow the code treats itWatch for
Lower-power equipmentSmaller nameplate on the heat pump, dryer, water heater or charger. The load on the worksheet drops.Nameplate goes into the calculation, so a lower rating counts directly.Comfort and performance for the room or house. Quote the real unit, not a placeholder.
Circuit sharingTwo loads on one circuit with a switch that allows only one at a time. Lawrence Berkeley National LaboratoryNEC 220.60 lets the calculation count only the larger of two loads that will not run together. Lawrence Berkeley National LaboratoryA listed control, and an inspector who accepts it. LBNL notes the 2026 NEC explicitly allows listed controls for this. Lawrence Berkeley National Laboratory
Load-balancing EV chargerOne charger or one circuit feeds two cars, and power is shared between them.Only the rating of the charger or the control setting counts (220.70 and 625.42(B) in the 2023 NEC). Lawrence Berkeley National LaboratoryUse the manufacturer's listed setting, not a guess.
Load-shed relayA relay switches off a controlled load, with a metering clamp on the service wires.An energy management system. Control setting at 80% of the service. Lawrence Berkeley National LaboratoryWhich load is shed, and whether it restarts correctly.
Smart breakersControl individual circuits, with timers or signals from total panel power.Also treated as an energy management system: 220.70 in the 2023 NEC, 120.7 in the 2026 edition. Lawrence Berkeley National Laboratory Lawrence Berkeley National LaboratoryExtra breaker spaces: in some systems two for the device, two for the control module and two for metering. Lawrence Berkeley National Laboratory
Smart panelControls loads to a service limit the installer sets and occupants cannot easily change. Lets you rank loads. Lawrence Berkeley National LaboratoryEnergy management system; the control setting at 80% becomes the service load for sizing. Lawrence Berkeley National LaboratoryInspector and utility acceptance; the cost of the panel; whether the existing service wires are healthy.
Service upgradeMore amps delivered to the house.Standard calculation on the new service size.Utility request, lead time, permit. How it works.

The code sections are LBNL's reading of the NEC: 220.60, 220.70 and 625.42 in the 2023 edition; 120.6, 120.7 and 130 in the 2026 edition, which Massachusetts enforces for permits granted after April 24, 2026. Mass.gov Mass.gov The state's amendment document we read does not modify those sections. Read the NEC free at nfpa.org; the inspector's reading governs.

Want a second opinion on whether you need a service upgrade?Send photos of the panel and meter and a list of the equipment you plan to add. Aurion tells you which route fits and prices it.
Send photos

How often do controls act?

LBNL says load control power interruptions are usually 15 minutes and almost always under an hour, and that most homes only need to control one or two devices to stay on a 100 or 200 amp service. Lawrence Berkeley National Laboratory An evaluation of nearly 1,000 U.S. homes found very few ever exceed 80% of their panel rating. Lawrence Berkeley National Laboratory The loads most worth controlling are EV chargers and water heaters. These are LBNL's findings, and they describe typical homes, not yours.

A breaker panel and a wall-mounted EV charger in a garage
EV chargers and water heaters are the loads LBNL names for control, and it says most homes only need to control one or two devices to stay on a 100 or 200 amp service. Lawrence Berkeley National Laboratory

Does anyone pay for the device?

Reading Municipal Light Department pays 100% of equipment cost up to $1,200 for load management devices: smart electrical panels, circuit control units, smart breakers and relays, or outlet splitters. Wiring, labor and installation are not covered. You enroll in its Residential Time-of-Use Schedule A2 rate for at least a year and let RMLD see the device's hourly data. Reading Municipal Light Department Reading Municipal Light Department Reading Municipal Light Department More in the rebates guide.

What we could not verify

  • Utility policy on the devices. We did not find an Eversource or National Grid page on smart panels, meter-side devices or load managers. Ask the utility if the device sits at or near the meter.
  • Inspector practice. The code allows these controls, but towns apply it themselves. Ask your inspector before you buy.
  • Prices. We do not give a price for smart panels or load managers. LBNL's guide does make one point worth knowing before you shop: if staying within the service is the only goal, a smart panel is probably an unnecessary and expensive option, and smart breakers can be a simpler, more cost-effective route when only one or two loads need control. Lawrence Berkeley National Laboratory

When a full upgrade is still the answer

Common questions

Can a smart panel let me skip a service upgrade?

Sometimes. Lawrence Berkeley National Laboratory says a smart panel is treated as an energy management system, and its control setting, set at 80% of the service or panel rating, becomes the home's service load for sizing. Whether your inspector accepts that for your job is theirs to decide, and the utility has its own rules for the meter. Ask both before you buy.

What is circuit sharing?

Two loads on one circuit with a switch that lets only one run at a time. LBNL's example is a clothes dryer and an EV charger on one 240 volt receptacle in a garage: the charger pauses while the dryer runs, then resumes. The code lets a load calculation count only the larger of two loads that will not run together (NEC 220.60), and the 2026 NEC explicitly allows listed controls for this.

Will a load manager turn my power off?

It turns off or reduces the loads it controls, not the house. LBNL says interruptions are usually about 15 minutes and almost always under an hour, and that an evaluation of nearly 1,000 U.S. homes found very few ever exceed 80% of their panel rating. Controlled loads are usually EV chargers and water heaters.

Is a smart breaker the same as a smart panel?

No. Smart breakers control individual circuits and have more limited abilities than a whole-panel system. LBNL notes that smart breakers managing current on the service may need extra breaker spaces: two for the device, two for the control module and two for the metering module. Count the spaces before you choose.

Does Massachusetts allow energy management systems in load calculations?

Massachusetts enforces the 2026 NEC with state amendments, effective April 24, 2026. LBNL says the 2026 NEC handles load controls in sections 120.6, 120.7 and 130 (the 2023 edition used 220.60, 220.70 and 625.42). The state amendment document we read does not change those sections. Your inspector decides what is acceptable on your job.

Is there a rebate for a smart panel or load manager?

Reading Municipal Light Department pays 100% of equipment cost up to $1,200 for a load management device, including smart panels, circuit control units, smart circuit breakers and relays, if you enroll in its time-of-use rate. We did not find a similar program on the other light plant pages we read, or an Eversource or National Grid rebate for the device itself.

Does a lower-power appliance really help?

It lowers the number on the nameplate, which lowers the calculated load. LBNL's worked examples for a new home with a 200 amp service cut the calculated service load by roughly 20 amps at 240 volts using lower-power appliances or a load-controlled EV charger. That was for a new-home reference case, so your house will differ.

When is a full service upgrade still the better answer?

When the loads exceed the service even with controls, when the panel has no physical space for the breakers you need, or when the panel is a safety concern. The DOE factsheet notes there are two limits: not enough physical space for breakers, or not enough electrical space. A fuse box, Federal Pacific or Zinsco panel changes the question again.

Back to the panel upgrade guide. Estimate first: 100A vs 200A. Call (781) 210-8400.

Heat pump coming and the panel is old?

Send a photo of the panel with the door open. We look at it and get back to you.

Send photos
Call (781) 210-8400Send photos